Click here to return to the MDOT homepage.
Maryland Crown Logo Click here to visit Governor's web site
 Contact Us Maryland Transportation Authority Search:  
Call 1-877-BAYSPAN For Current Bridge Traffic Conditions
Home
Traffic Information
Lane Closures
Toll Rate
Bay Bridge Fact Sheet
Safety Tips
Bay Crossing Task Force
Overview of Travel Inititive
Progress Report
Contact
Links


BAY BRIDGE RESURFACING PROJECT STATUS

The rehabilitation project for the deck of the westbound span of the Bay Bridge consists of two phases. The Phase I contract was focused on resurfacing major portions of the bridge deck and included some full-depth poured-in-place replacement for portions of the deck. Phase II of the project, which will complete the rehabilitation of the deck, is to use full-depth pre-cast deck replacement on the suspension and thru truss portions of the bridge span.

Phase I - Steps being taken to resolve the
"de-lamination" issue:


Numerous modifications to the original scope of work were implemented to eliminate a concrete overlay de-lamination problem. The problem was discovered in 2004 on some portions of the bridge deck where overlay, or resurfacing, work had been performed. Work modifications were provided to the Authority by a consultant who had been investigating the deck de-lamination issue since April of 2004. The Bay Bridge Overview Team, which was appointed by the Chairman, also provided guidance on the revised specifications.


The Overview Team completed their "Bay Bridge Deck Investigation" in January of 2005. Among the major changes were:

  • Enhanced surface preparation methods

  • New type of concrete overlay material (latex modified concrete)

  • Strict adherence to weather condition requirements relating to concrete placement and curing procedures.
The left lane of the westbound span of the bridge (lane #3) had all the original deck overlay, or resurfacing, work replaced during the months of September and November 2004. Ongoing testing and inspection of this work is underway to ensure we have a good product. This appears to be very successful.

Portions of the center lane resurfacing (lane #2) that has de-laminated were resurfaced this spring. The center lane work, included some first-time resurfacing and full-depth cast-in-place replacement work (original to the Phase I scope).

The right lane (lane #1) of the original resurfacing work shows very minor concrete de-lamination at this time. Per recommendations of the Overview Team, this lane is being inspected regularly and evaluated to assure it is performing well. Maintenance and nominal repairs are routinely scheduled in this lane through the fall. Preventive deck sealing also is scheduled to continue through the fall. Ongoing patching of the portions of the bridge deck that will be replaced under Phase II will continue until Phase II work is completed.

Phase II - rehabilitation of the remaining portions of the bridge deck using full-depth pre-cast deck replacement techniques. No 24/7 lane-closures will be needed for this work:

An initial bid for the Phase II work was rejected by the Authority in January 2005. Phase II of the project was advertised in September, with a contract awarded in spring 2006 and construction starting in fall 2006. The scope and construction options to complete this phase have undergone a peer review process. The contract incorporates results of ongoing deck analysis, recommendations of the Overview Team and peer review efforts. Some of the items addressed include:

1)Modified the deck-replacement system and methodology.

2)
Added full-depth replacement of more lightweight concrete spans (as recommended by the Overview Team).

3)
Conducted outreach to contractors for feedback on project specifications (constructability).

4)
Re-examined the MBE goals.

5)
Lengthened contract duration.

Background of Bridge and Project Scope

The Westbound William Preston Lane, Jr. Memorial Bridge (Bay Bridge) carries three lanes of traffic on U.S. 50 over the Chesapeake Bay from the eastern shore of Maryland to the state’s mainland near Sandy Point, Maryland. The bridge was opened to traffic in 1973 and compliments the original two-lane bridge over the Chesapeake Bay, which was built in 1952. The four-mile long, 38 feet wide bridge consists of five different types of structural components, including pre-stressed concrete beams at each end, steel girders, two steel deck trusses, a three span suspension unit, and a three span steel through truss unit. In all, there are 122 spans (sections) within the length of the bridge.

The Bay Bridge Deck Renovation Project involves two deck rehabilitation methods: resurfacing (replacing the top two inches) and complete replacement, which includes poured in place concrete and pre-cast concrete segments. In addition, the roadway joints and steel railings are being rehabilitated, and a fiber optic conduit line has been installed.

Late 1990’s
The original 6" to 7" thick reinforced concrete deck at the westbound bridge began to exhibit deterioration that warranted initiating a major rehabilitation program.

Contract Design Phase (2000-2001)
An intense planning and design effort commenced to rehabilitate the deck and steel railing on the bridge. The Maryland Transportation Authority, in conjunction with several engineering consultants, performed several detailed investigations of the condition of the deck in order to develop an appropriate rehabilitation project.
A physical deck evaluation was conducted in 2000 to determine the condition of the concrete by taking core samples at many representative areas on the bridge.

Data such as the percentage of sound concrete, average concrete compressive strength, and chloride content of each core sample was gathered to assess the deck’s general condition. This study supplemented a thorough investigation of the bridge deck performed in 1993. Both physical deck evaluations were performed by Maryland’s SHA Laboratory.

The consultant recommended that the concrete deck at most (95) of the spans on the bridge required resurfacing the top 2 inches of concrete. It was determined the deck needed to be completely replaced at several (27) of the larger components on the bridge, such as the 3000 foot long 3 span suspension span unit, the entire steel through truss, and the 3000 foot long curved steel girder section on the western half of the bridge.

Because of the enormity of this project, the Authority determined that this rehabilitation effort should be divided into two separate construction contracts spanning over a four-year time frame.

Contract Procurement Phase (June 2001 – January 2002) and Contract Specifics
The first Contract was advertised in June 2001. The contract was awarded to Cianbro on October 15, 2001. In November 20, 2001 the Authority exercised an option to add fiber optic conduit to the contract. Execution of the contract by Cianbro Corporation was in December 2001, for $33.5 million. It includes resurfacing the deck at 80 of the 92 pre-stressed concrete beam (approach) spans, three (3) deck truss spans, and three (3) of the 12 steel girder spans. In addition, the deck is being fully replaced with cast-in-place concrete in 21 spans; all located within the pres-stressed concrete beam and steel girder units of the bridge.

In the resurfacing portion of the project, the contract specifications allowed for the Contractor to select from three concrete mix options: latex modified concrete (LMC), micro silica concrete, or high performance concrete.

Most of the work takes place after Labor Day but prior to Memorial Day in order to avoid the extremely high volume of traffic that uses the bridge during the summer season. The Contractor has been permitted to close one lane continuously for construction during the off-season months, from approximately October 15 through April 15 each year. During nighttime hours, a second lane or the entire bridge has been closed in order to pour concrete and perform other construction activities. However, no weekend lane closures are allowed during June, July, and August.

In addition, all three lanes on the bridge were required to be opened to traffic during the Easter and Thanksgiving holiday weekends. In consideration of both maintenance of traffic and safety of the contractors, the travel lanes have been shifted and their widths reduced to accommodate a workable construction zone. A movable concrete traffic barrier has been utilized to facilitate lane closures and phased construction.

As a result of these lane closure restrictions, all the work in this project has been constructed in three phases (i.e. one lane at a time). A micro silica concrete mix is being used for the overlay areas since this material has the capability to cure quickly in colder temperatures than traditional concrete mixes. In addition, the Authority required a two-year warranty on the concrete resurfacing portion of the project.

The current contract amount, including approved extra work to date, is $43.5 million. The extra work includes additional railing rehabilitation, resurfacing, and other miscellaneous work.

Construction Timeline
January to Spring 2002 - Work began in the center lane of the bridge, with both deck replacement and resurfacing operations.

Fall 2002 through Spring 2003 - Cianbro closed the left lane of the bridge and rehabilitated the entire deck within the entire contract limits.

Spring and Fall months in 2003 - The contractor performed extra work to resurface more than 4000 feet of the deck (9 spans of deck truss) between the two channel spans.

Fall 2003 through Spring 2004 - Cianbro closed the right lane of the bridge and rehabilitated the entire deck within the entire contract limits.

Work remains to be completed in the center lane, including some overlay, joint replacements, and deck replacement.

Resurfacing Problems - Timeline
December, 2003 – Construction inspectors identified random, isolated concrete cracking in the deck.

February to March, 2004 – Construction inspectors noticed increased areas and amounts of concrete cracking in the deck.

Spring 2004 – Construction inspectors noticed widespread concrete cracking in the deck, contained in the center and left lanes of the bridge. Construction personnel documented the extent of the deterioration.

March 2004 through Present - The consulting firm of O’Connell and Lawrence, Inc. (OC&L) was contracted to perform an independent investigation regarding the concrete cracking conditions in regards to the actual cause as well as appropriate solutions to remedy the problems. A task order for this work began in April. OC&L has performed field and laboratory testing on the concrete deck in the left lane. Meetings amongst the Authority, OC&L, the original design consultant, and the contractor began in March and have continued to date.


Other Investigative Work and Reports conducted and performed by OC&L:

- Over 370 small concrete "cores"(samples) have been extracted from the deck of lane 3. Laboratory tests have been conducted on these samples in an effort to ascertain the possible causes and failure mode of the concrete.

- Test "patching" sections have been performed on the deck in order to provide more information regarding appropriate surface preparation methods to use prior to placing a new concrete material over the existing deck.

- June, 2004 - Initial findings of concrete cracking in deck submitted to Authority

- August 18 and 20, 2004 - OC&L submitted letter to Authority with preliminary recommendations of the use of LMC as well as a more intensive surface preparation method for future overlay work.

- September 2, 2004 – The Authority Capital Committee was briefed. They requested repairs begin immediately with LMC and that weekend closures be utilized if it proved necessary to complete the work.

- September 3, 2004 – OC&L submitted Preliminary Report of Findings to the Authority.

Other Developments
September 10, 2004 – A peer review panel consisting of Authority, SHA, Virginia Transportation Research Council, and OC&L personnel convened and concurred with findings of the Preliminary Report.

September 10, 2004 - A press release was issued stating that the left lane of the bridge will be closed continuously until November 24 (Wednesday before Thanksgiving).

September 13, 2004 – Contractor closed the left lane of bridge with concrete barriers, to mill (scrape) 2 inches off the top surface of deck, perform surface preparation procedures as recommended by OC&L. Cianbro contracts GA & FC Wagman, Inc. to perform LMC (latex modified concrete) overlay placement operations, which would take place after the deck surface has been adequately milled and the surface has been prepared.

September 20, 2004 – Baltimore Sun contacted Authority inquiring about the lane closures and the resurfacing issue.

For current conditions at the bridge 24 hours-a-day, contact the BAYSPAN hotline at 1-877-229-7726, or Click here to view real-time camera images from the bridge’s approaches


Page Last updated January 03, 2006


MDTA

EZ-Pass